In short: To build the largest hydraulically filled dam in the United States, engineers used electric dredges to pump sediment into place. But in 1938, a terrifying structural failure proved that even the most massive infrastructure projects face unpredictable geological risks.

Construction of the Fort Peck Dam began in 1933 as a major Public Works Administration project during the Great Depression. At its height in July 1936, the project employed 10,546 workers. To build the structure, engineers utilized four electric dredges to pump material from nearby borrow pits, a process known as hydraulic fill. This method created a massive structure over 250 feet high and 21,026 feet long, eventually forming Fort Peck Lake, which is the fifth largest artificial lake in the country.

The project faced a catastrophic setback on September 22, 1938. During construction, a section of the dam began to settle, causing cracks to appear 30 feet below the crest. A massive slide occurred, with the upstream shell moving into the reservoir and a breach forming in the core pool. The disaster claimed the lives of eight men, including six who were never recovered and remain entombed within the structure. The slide was so rapid that a construction supervisor reported the advancing scarp moved at approximately 10 mph.

Investigations by the U.S. Army Corps of Engineers sought to identify the cause of the failure. While several theories were considered—including liquefaction of the sand or the core material—researchers ultimately pointed to the geology beneath the dam. The site sits atop Bear Paw shale, which contains thin layers of bentonite. High water pressure caused by the weight of the new fill likely increased pore pressure in these bentonite seams, drastically reducing their shear strength and triggering the slide.

Opens the Intellect+ feed with this card first. Swipe up for the next one.

Sources

To cite this card, link to https://intellectplus.co.uk/app/technology-fort-peck-dam.

How we source, check and correct cards: Editorial standards.

General information, not professional advice. Spotted an error? Flag the card or see corrections and complaints.

Intellect Plus is a visual educational discovery platform for exploring fascinating facts and ideas. Brain Food, Not Brain Rot. What is Intellect Plus?

Related

Finding something worth knowing…