Why spending half your budget doesn't mean you're halfway done

Why spending half your budget doesn't mean you're halfway done
Image: Intellect (generated)

In short: A project manager reports that 50% of the budget is spent exactly six months into a one-year plan. It looks like perfect progress, but it could actually be a disaster. Without measuring objective technical performance, you cannot distinguish between a project running ahead of schedule and one spiraling into failure.

Earned Value Management (EVM) is a project management technique designed to provide an objective measure of progress by integrating three critical dimensions: scope, time, and cost. At its core, EVM solves the 'illusion of progress' problem. For example, if a project spends 50% of its budget but has only completed 25% of the work, it is failing; conversely, if it has completed 75% of the work for that same spend, it is excelling. EVM provides the mathematical framework to surface these discrepancies by comparing Planned Value (PV) against Earned Value (EV).

Frank and Lillian Gilbreth's 'earned time' concepts formed the basis for this approach, which first appeared within factory production during the early 1900s. It gained prominence in U.S. government programs during the 1960s as a way to manage complex contracts. By the late 1980s, it transitioned into a broader management methodology used by executives and industrialized nations alike. Because EVM identified specific operational flaws, Secretary of Defense Dick Cheney terminated the Navy A-12 Avenger II Program in 1991, highlighting its significance to top officials.

Modern EVM implementations vary based on project complexity. While a simple version can be managed via spreadsheets to track technical performance, large-scale projects require quantitative forecasts of cost and schedule performance. For these complex systems, costs must be verifiable, objective, and granular—often requiring agreement between all involved parties on local market rates for labor and materials. By plotting cumulative costs against time and comparing them to the 'earned' progress curve, managers can identify whether a project is truly under budget or simply moving too slowly.

Opens the Intellect+ feed with this card first. Swipe up for the next one.

Sources

To cite this card, link to https://intellectplus.co.uk/app/health-earned-value-management.

How we source, check and correct cards: Editorial standards.

General information, not professional advice. Spotted an error? Flag the card or see corrections and complaints.